NLMK | 10 August 2007 г. | 14:53

NLMK upgrades its hot rolled production facilities

NLMK upgrades its hot rolled production facilities
NLMK has commissioned reheating furnace # 4 following its reconstruction for heating slabs before hot rolling.  The furnace, which has a capacity of 320 tonnes of steel per hour, will allow a 50% reduction in energy consumption (natural and Blast Furnace gas) decrease environmental impacts by almost 30%.
Reheating furnace # 4 is the second furnace at the production site in Lipetsk (reconstructed furnace # 5 was commissioned in 2004).  The design features provide high quality slab heating and flats production by using state-of-the-art resource-saving and environmentally friendly technologies.
The unique performance capabilities of the furnace (low steel losses and high uniformity of reheating) allow it to process products for both carbon and grain-oriented steel production. 
This project, implemented within the framework of the NLMK’s Second Phase of Technical Upgrading Programme, is worth over RUR1.5 billion 
 
Source: Metal Supply and Sales
View count: 106